SRINAGAR: Minister for Power Development Department (PDD), Revenue, Law and Parliamentary Affairs, Disaster Management, Relief, Rehabilitation and Reconstruction (DMRRR) and Elections, Ali Mohammad Sagar, on Thursday directed the concerned departments and executing agencies to prepare a revised Detailed Project Report (DPR) for the new High Court Complex at Rakh-Arth, Bemina Bypass, incorporating updated cost estimates, technical requirements and a realistic phase-wise execution schedule.
The directions were issued during an extensive review of the ongoing construction project, during which the Minister inspected the site, assessed the pace of work and reviewed its physical and financial progress. He also sought detailed feedback from the executing agencies on the status of different project components and the requirements for completing the work within the stipulated timeframe.
Officials informed the Minister that the project, which commenced in April 2022, has an approved estimated cost of ₹908.20 crore, against which an expenditure of ₹213.50 crore has been incurred so far. The main building has achieved approximately 65 per cent physical progress and has an estimated cost of around ₹450 crore, while the road component accounts for approximately ₹90 crore.
Phase-I of the project is targeted for completion by November 2027, with the first block expected to be completed within the next six months. The tender for installation of air-conditioning and heating systems has been allotted, while the electrical works have also been tendered.
During the review of the project’s financial requirements, Sagar was informed that approximately ₹290 crore would be required to meet the expenditure up to November 2027. The budget provision for 2026-27 includes ₹87 crore under the Special Assistance to States for Capital Investment (SASCI) and ₹5.30 crore under the Union Territory Capex. An additional requirement of ₹41 crore has been proposed under the Budget Estimates for 2027-28.
Emphasising the need to revisit the original DPR, Sagar directed the concerned officers to account for the time elapsed since the project’s commencement, changes in prevailing market rates, updated technical requirements and the financial implications of the remaining works.
He called for a comprehensive reassessment covering the project’s overall scope, technical specifications, pending components and revised cost estimates. The updated DPR, along with a realistic phase-wise execution schedule, is to be prepared for consideration and approval by the competent authority.
The Minister stressed that adequate financial planning and timely availability of funds would be essential to sustain the pace of construction and prevent delays. He also directed the executing agencies to strengthen coordination, ensure close monitoring of individual project components and maintain accountability at every level.
Sagar further stressed that construction quality, compliance with technical specifications and timely execution should remain key priorities, given the long-term institutional requirements of the judicial infrastructure project.
Officials also informed the Minister that Phase-II of the High Court Complex would be taken up separately through the prescribed tendering process.
The Minister was accompanied during the inspection by the Chief Engineer, Roads and Buildings (R&B), Central; Director Litigation, Kashmir; the concerned Executive Engineer; and Assistant Executive Engineers.