Home TOP NEWS

LG reviews summer preparedness of Power Department

Images News Netwok by Images News Netwok
May 27, 2021
in TOP NEWS
A A
0
LG reviews summer preparedness of Power Department
FacebookTwitterWhatsapp

Jammu: Lieutenant Governor Manoj Sinha today chaired a high level meeting to review the preparedness of Power Department for Jammu division in view of the ongoing summer season.

During the meeting, which was attended by senior officers of Jammu Power Distribution Corporation Limited (JPDCL), and J&K Power Transmission Corporation Limited at Raj Bhavan, the LG issued directions to streamline the power transmission and distribution system in the UT.

Related posts

   First-ever freight train carrying cement arrives at Anantnag Goods Shed

  First-ever freight train carrying cement arrives at Anantnag Goods Shed

August 10, 2025
Govt bringing laws, taking steps to make social media platforms accountable: IT Min

Goods train to Kashmir a milestone: Ashwini Vaishnaw

August 10, 2025

Stressing on speeding up the process of replacement of damaged transformers to avoid inconvenience to the people, the LG fixed an 8 hour deadline for replacement of damaged transformers in urban areas, while rural areas will get transformers replaced within 48 hours.

“Adopt a futuristic approach, make procurements in advance and fix responsibilities for delays, besides taking corrective measures to provide consumers with the requisite facilities,” the LG asked the Power Department.

He emphasized on urgent re-examining of short-term and medium-term measures to minimize disruption in supply, network resilience, besides developing better synergy between officials at all levels.

In order to make the repair and replacement working more effective, the meeting decided that the transformers would get a Unique Identification number with details of installations and repairs. One month’s timeline was fixed for preparing an online system for inventory management, executing a meter reading application for streamlining the process of power consumption, billing and collection.

The LG asked the concerned officers to rationalize the buffer stock of inventory in all districts in order to reduce the replacement time.

“Speed up the process of replacement of non-functional power infrastructure. Prioritize areas with more power consumption; put power curtailment schedules in public domain and address the issues of power outage in villages,” LG directed the officers.

Directions were also passed to senior officials for monitoring of up-gradation work of grid stations, strengthening of distribution mechanism, transmission lines, while concentrating on immediate needs of power supply, focusing on maintenance of transmission and distribution networks.

The LG also directed the officers to take all necessary measures to reduce the transformers’ damage rate, besides upgrading the infrastructure to reduce instances of disruption causing power outages.

While taking the status of power supply to oxygen generation plants, LG directed the concerned officials to ensure uninterrupted power supply with backup to the oxygen plants.

He also directed for making the response mechanism for power restoration prompt and more effective to ensure optimum power supply to every household in the summers.

The LG also took a detailed overview of the total installed transformation capacities and peak demand met in Jammu division during summer of 2020 and anticipated for summer of 2021.

He assessed the present status of category-wise power consumers, district-wise power demand and supply position in Jammu, buffer stock of distribution transformers, augmentation of receiving stations, procurement of spares & inventory, status of branch cutting/trimming of trees, the press release informed.

Principal Secretary PDD, Rohit Kansal briefed the LG about preparedness of the department for the summer season, besides status of various projects for augmentation of power infrastructure in Jammu division, including commissioning of 220 KV LILO-I Interconnection with PGCIL  Jatwal , construction of 160 MVA 220/66  KV GSS Ghatti, Kathua along with its associated 220 Kv D/C Thein- Hiranagar Transmission line, construction of 160 MVA 220/66  KV GSS, Samba along with its associated 220 Kv D/C Jatwal-Samba Transmission line, capacity addition works at GSS Barn , capacity addition works at GSS Canal, capacity addition works at GSS Gladni.

Previous Post

LG calls for 100% saturation of social security schemes

Next Post

JEE-Advanced postponed due to COVID-19 situation

Images News Netwok

Images News Netwok

Next Post
KU postpones all exams scheduled on April 2,  suspend classwork

JEE-Advanced postponed due to COVID-19 situation

Leave a Reply Cancel reply

Your email address will not be published. Required fields are marked *

ePaper

  • About us
  • Contact us
  • Our team
  • Terms of Service
E-Mailus: kashmirimages123@gmail.com

© 2024 Kashmir Images - Designed by GITS.

No Result
View All Result
  • TOP NEWS
  • CITY & TOWNS
  • LOCAL
  • BUSINESS
  • NATION
  • WORLD
  • SPORTS
  • OPINION
    • EDITORIAL
    • ON HERITAGE
    • CREATIVE BEATS
    • INTERALIA
    • WIDE ANGLE
    • OTHER VIEW
    • ART SPACE
  • Photo Gallery
  • CARTOON
  • EPAPER

© 2024 Kashmir Images - Designed by GITS.