• TOP NEWS
  • CITY & TOWNS
  • LOCAL
  • BUSINESS
  • NATION
  • WORLD
  • SPORTS
  • OPINION
    • EDITORIAL
    • ON HERITAGE
    • CREATIVE BEATS
    • INTERALIA
    • WIDE ANGLE
    • OTHER VIEW
    • ART SPACE
  • Photo Gallery
  • CARTOON
  • EPAPER
Sunday, July 6, 2025
Kashmir Images - Latest News Update
Epaper
  • TOP NEWS
  • CITY & TOWNS
  • LOCAL
  • BUSINESS
  • NATION
  • WORLD
  • SPORTS
  • OPINION
    • EDITORIAL
    • ON HERITAGE
    • CREATIVE BEATS
    • INTERALIA
    • WIDE ANGLE
    • OTHER VIEW
    • ART SPACE
  • Photo Gallery
  • CARTOON
  • EPAPER
No Result
View All Result
Kashmir Images - Latest News Update
No Result
View All Result
Home TOP NEWS

Will take three days to setup Bailey bridge in Ramban: BRO official

Images News Netwok by Images News Netwok
January 15, 2021
in TOP NEWS
A A
0
Traffic on Highway to remain suspended for next 10 days: Officials
FacebookTwitterWhatsapp

Srinagar: The Border Roads Organization (BRO) would complete setting of Bailey bridge near Kela Morh in next three days along the 270-km Jammu-Srinagar national highway to restore connectivity between the twin capital cities.

A portion of the highway sank near Kela Morh in Ramban district after a concrete retaining wall of a bridge collapsed on Sunday evening.

Related posts

Over 20,000 pilgrims visit Amarnath shrine in first 2 days of Yatra: LG Manoj Sinha

Over 20,000 pilgrims visit Amarnath shrine in first 2 days of Yatra: LG Manoj Sinha

July 5, 2025
Union Agri minister urges ‘everyone to come and see Kashmir’

Union Agri minister urges ‘everyone to come and see Kashmir’

July 5, 2025

The Bailey bridge is being launched by BRO as an interim measure to restore connectivity between Srinagar and Jammu.

“It will take two to three days more to setup bailey bridge. Heavy vehicles carrying essential supplies can also be allowed to cross over the bridge,” local news agency KNS quoted Commanding Officer of 99 RCC Vinyak Project Beacon as saying

He added that it will provide relief to the hundreds of vehicles carrying essentials to the Valley.

Officials of National Highway Authority of India (NHAI), the road construction and maintaining agency, had earlier said that “repairing by concrete filling and settling of the concrete for making it (highway) motorable may take approximately ten days.”

Meanwhile, another news agency KNO quoted Purshotam Kumar, Project Director NHAI as saying: “As far as the Bailey bridge is concerned we are expecting it will be completed by tomorrow.”

Previous Post

JKSFC renamed as Jammu & Kashmir and Ladakh Finance Corporation

Next Post

Naeem Akhtar hospitalized after falling unconscious in Srinagar sub-jail

Images News Netwok

Images News Netwok

Next Post
Naeem Akhtar condoles demise of Kashmiri artist Prithvi Nath Koul

Naeem Akhtar hospitalized after falling unconscious in Srinagar sub-jail

Leave a Reply Cancel reply

Your email address will not be published. Required fields are marked *

ePaper

  • About us
  • Contact us
  • Our team
  • Terms of Service
E-Mailus: [email protected]

© 2024 Kashmir Images - Designed by GITS.

No Result
View All Result
  • TOP NEWS
  • CITY & TOWNS
  • LOCAL
  • BUSINESS
  • NATION
  • WORLD
  • SPORTS
  • OPINION
    • EDITORIAL
    • ON HERITAGE
    • CREATIVE BEATS
    • INTERALIA
    • WIDE ANGLE
    • OTHER VIEW
    • ART SPACE
  • Photo Gallery
  • CARTOON
  • EPAPER

© 2024 Kashmir Images - Designed by GITS.