• TOP NEWS
  • CITY & TOWNS
  • LOCAL
  • BUSINESS
  • NATION
  • WORLD
  • SPORTS
  • OPINION
    • EDITORIAL
    • ON HERITAGE
    • CREATIVE BEATS
    • INTERALIA
    • WIDE ANGLE
    • OTHER VIEW
    • ART SPACE
  • Photo Gallery
  • CARTOON
  • EPAPER
Wednesday, July 2, 2025
Kashmir Images - Latest News Update
Epaper
  • TOP NEWS
  • CITY & TOWNS
  • LOCAL
  • BUSINESS
  • NATION
  • WORLD
  • SPORTS
  • OPINION
    • EDITORIAL
    • ON HERITAGE
    • CREATIVE BEATS
    • INTERALIA
    • WIDE ANGLE
    • OTHER VIEW
    • ART SPACE
  • Photo Gallery
  • CARTOON
  • EPAPER
No Result
View All Result
Kashmir Images - Latest News Update
No Result
View All Result
Home CITY & TOWNS

Secy I&FC reviews progress on Phase 1 of Flood Management project

KI News by KI News
December 11, 2018
in CITY & TOWNS
0
Secy I&FC reviews progress on Phase 1 of Flood Management project

SRINAGAR, DECEMBER 10: The Secretary to Government PHE, Irrigation and Flood Control Department (I&FC), Farooq Ahmad Shah today reviewed the progress on Phase 1 of ongoing Flood Management project.

The re-sectioning of Flood Management project Phase 1 coming up at Rs 399 crore from Padshahi Bagh to Wular is aimed at increasing the discharge capacity of flood channel and is set to be completed by March 2019.

Related posts

Deputy CM reviews SANJY-2025 arrangements via Baltal axis

Deputy CM reviews SANJY-2025 arrangements via Baltal axis

July 2, 2025
Sakeena Itoo credits SKIMS’s founding to Sher-i-Kashmir

Sakeena Itoo credits SKIMS’s founding to Sher-i-Kashmir

July 2, 2025

The Secretary was briefed that the salvage of the causeway at Mehjoor Nagar Bridge including pipes and pile heads are being removed at a fast pace.

He was also informed that the re-sectioning work is going on in full swing from Padshahi Bagh to Hokersar including Shariefabad. It was added that the re-sectioning of Flood Spill Channel at Naidkhai is also in progress and land acquisition is almost complete.

On seeking the details regarding construction of two bridges at NaidKhai and Shariefabad, the concerned officers assured the Secretary that the same will also be completed by March 2019.

Shah was further informed that the beautification of river Jehlum at Srinagar is on and the project costs about Rs 5 crore.

The Secretary said an advance action on Phase 2 has also been started for which project enforcing agency WAPCOS has assured that the DPR for it will be submitted within 15 days.

He said that the government has already committed to start the project by next season and all the concerned are directed to complete and wind up phase 1 by March 2019.

During the meeting, the procurement of pipes for Tral LIS was also discussed and the EX. Engineer S.E assured that the tenders will be finalized in 25 days.

The Secretary warned that no lapse would be tolerated in meeting the deadline of the projects.

He later visited Mehjoor Nagar Bridge and other sites for on the spot inspection of the ongoing works.

Previous Post

IOC invites application for retail outlet dealership

Next Post

J&K team shines at AEP Role Play Competition

Next Post
J&K team shines at AEP Role Play Competition

J&K team shines at AEP Role Play Competition

Leave a Reply Cancel reply

Your email address will not be published. Required fields are marked *

ePaper

  • About us
  • Contact us
  • Our team
  • Terms of Service
E-Mailus: [email protected]

© 2024 Kashmir Images - Designed by GITS.

No Result
View All Result
  • TOP NEWS
  • CITY & TOWNS
  • LOCAL
  • BUSINESS
  • NATION
  • WORLD
  • SPORTS
  • OPINION
    • EDITORIAL
    • ON HERITAGE
    • CREATIVE BEATS
    • INTERALIA
    • WIDE ANGLE
    • OTHER VIEW
    • ART SPACE
  • Photo Gallery
  • CARTOON
  • EPAPER

© 2024 Kashmir Images - Designed by GITS.