• TOP NEWS
  • CITY & TOWNS
  • LOCAL
  • BUSINESS
  • NATION
  • WORLD
  • SPORTS
  • OPINION
    • EDITORIAL
    • ON HERITAGE
    • CREATIVE BEATS
    • INTERALIA
    • WIDE ANGLE
    • OTHER VIEW
    • ART SPACE
  • Photo Gallery
  • CARTOON
  • EPAPER
Saturday, July 5, 2025
Kashmir Images - Latest News Update
Epaper
  • TOP NEWS
  • CITY & TOWNS
  • LOCAL
  • BUSINESS
  • NATION
  • WORLD
  • SPORTS
  • OPINION
    • EDITORIAL
    • ON HERITAGE
    • CREATIVE BEATS
    • INTERALIA
    • WIDE ANGLE
    • OTHER VIEW
    • ART SPACE
  • Photo Gallery
  • CARTOON
  • EPAPER
No Result
View All Result
Kashmir Images - Latest News Update
No Result
View All Result
Home CITY & TOWNS

Div Com reviews status of major road, bridge projects in Srinagar

Images News Netwok by Images News Netwok
April 20, 2018
in CITY & TOWNS
A A
0
Div Com reviews progress of Swachh Bharat Mission
FacebookTwitterWhatsapp

SRINAGAR, ARIL 19: Divisional Commissioner Kashmir, Baseer Ahmad Khan today visited Rajbagh and Mahjoor Nagar localities here to review the status of mega road and bridge projects under construction in these areas.

The Div Com directed the officials of various departments to work in tandem so that the pace of development projects is expedited. District Development Commissioner Srinagar, Dr Syed Abid Rashid Shah and other concerned officers from line departments accompanied the Div Com.

Related posts

Sakeena Itoo visits Shahoo Kulgam, reviews arrangements for 10th Muharram

Sakeena Itoo visits Shahoo Kulgam, reviews arrangements for 10th Muharram

July 5, 2025
Omar Abdullah-led govt committed to balanced development of all regions of J&K: Javed Rana

Rana pays tributes to Imam Hussain (AS), Karbala martyrs

July 5, 2025

The Div Com directed the SMC officials to undertake massive demolition drive starting from old Zero Bridge against the illegal encroachments that are hampering the progress of the work. He said that the road will go a long way in decongesting the intra-city and inter-district traffic. He said that the 10.5 km road widening project will start from Zero Bridge and reach IG road via Bund and government is keen to complete it within shortest possible time.

He directed the police to provide the required support to make the demolition drive successful and complete it in three days. He asked the DDC Srinagar to monitor the demolition drive on daily basis.

Later, the Div Com also visited the under construction Mahjoor Nagar bridge where he was informed that majority of works on the bridge has been completed. The Div Com said that the bridge is slated to be thrown open to traffic by May 05 and directed the constructing agency to finish the final works on time.

Previous Post

Tourism deptt to promote tourist AC coach

Next Post

Tassaduq Mufti calls for preserving JK’s distinct heritage character

Images News Netwok

Images News Netwok

Next Post
Tassaduq Mufti calls for preserving JK’s distinct heritage character

Tassaduq Mufti calls for preserving JK’s distinct heritage character

Leave a Reply Cancel reply

Your email address will not be published. Required fields are marked *

ePaper

  • About us
  • Contact us
  • Our team
  • Terms of Service
E-Mailus: [email protected]

© 2024 Kashmir Images - Designed by GITS.

No Result
View All Result
  • TOP NEWS
  • CITY & TOWNS
  • LOCAL
  • BUSINESS
  • NATION
  • WORLD
  • SPORTS
  • OPINION
    • EDITORIAL
    • ON HERITAGE
    • CREATIVE BEATS
    • INTERALIA
    • WIDE ANGLE
    • OTHER VIEW
    • ART SPACE
  • Photo Gallery
  • CARTOON
  • EPAPER

© 2024 Kashmir Images - Designed by GITS.