Jammu: Chief Secretary Dr Sajjan Singh Yadav on Friday reviewed the progress of major road infrastructure projects in Jammu and Kashmir, stressing timely execution, interdepartmental coordination, construction quality and improved connectivity, particularly in remote, border and hilly areas.
Chairing a review meeting of the Public Works (Roads and Buildings) Department, he assessed ongoing projects, development schemes and the department’s future roadmap. The meeting was attended by senior officers, including the Additional Chief Secretary, PWD; Divisional Commissioners of Jammu and Kashmir; Secretary, Transport Department; Engineer-in-Chief, PWD; Regional Officer, NHAI; and Chief Engineers of Project Beacon and Project SAMPARK. Deputy Commissioners participated through video conferencing.
Additional Chief Secretary, PWD, Anil Kumar Singh informed the meeting that J&K has a road network of approximately 42,121 kilometres, while its overall infrastructure portfolio is valued at ₹1.28 lakh crore, covering ongoing, sanctioned and proposed projects.
Under the National Highway programme, 43 works worth ₹39,784 crore are under execution, 11 sanctioned works worth ₹9,187 crore are awaiting commencement, and another 31 projects involving ₹70,839 crore are at the DPR or in-principle stage.
The meeting was informed that the Z-Morh Tunnel is operational, while the Zojila Tunnel has achieved 49.64 per cent physical progress following its main breakthrough on June 9, 2026. Work on the Vailoo-Donipawa four-laning project has also commenced.
Srinagar Ring Road Phase-I and the tunnels on Jammu Ring Road have each achieved around 92 per cent progress. The Pulwama Bypass, Sanat Nagar Flyover and Tengpora service road have been completed.
The meeting also reviewed the proposed 12.85-km Sudhmahadev-Dranga Tunnel, estimated at ₹4,179.18 crore, and the 38.61-km Singhpora-Vailoo Tunnel, costing ₹5,600.28 crore. Land acquisition for both is under process. Other strategic tunnel proposals, including Pir Ki Gali, Sadhna, Keran, Machil and Gurez, were also discussed.
Project SAMPARK on NH-144A (Akhnoor-Poonch) has achieved 90.35 per cent length-weighted physical progress, with two of its eight packages completed.
Under PMGSY-IV, 644 roads covering around 3,357 kilometres have been sanctioned to connect 789 eligible habitations by March 2028.
Reviewing financial progress, the meeting was informed that against the UT Capex allocation of ₹5,969.55 crore for 2026-27, ₹4,061.07 crore had been released and ₹2,142.13 crore spent as on November 20.
Under CRIF, 294 projects worth ₹4,337.21 crore have been sanctioned, with 203 completed up to March 2026. NABARD-RIDF has sanctioned 1,074 projects worth ₹4,967.70 crore, of which 427 had been completed by March 2026.
The department also reported completion of 2,046 flood-restoration works between April 1 and October 31, 2026. During April-October, 1,500 kilometres of roads were macadamised, 68 identified black spots rectified and 1,265 road safety audits conducted.
Of the 6,000 migrant transit accommodation units, 5,288 had been completed and handed over to the Department of Disaster Management, Relief, Rehabilitation and Reconstruction.
The Chief Secretary stressed effective coordination, optimal utilisation of resources and quality construction, underscoring the need to strengthen last-mile connectivity while ensuring that infrastructure can withstand the region’s challenging climatic and geological conditions.