CS reviews progress of Jhelum & Tawi Flood Recovery Project

Decrease Font Size Increase Font Size Text Size Print This Page

SRINAGAR: Chief Secretary, Atal Dulloo, today chaired a review meeting here at the Civil Secretariat to assess the progress on the World Bank-funded Jhelum and Tawi Flood Recovery Project (JTFRP).

Chief Executive Officer of the Economic Reconstruction Agency (ERA), Dr Sehrish Asgar, presented a detailed report highlighting significant milestones achieved, so far.

During the meeting, it was informed that the proposals for additional works from six line departments were submitted to the World Bank, with four proposals receiving approval from the World Bank. Besides, the discussions focused on expediting the completion of the Bone and Joint Hospital and other crucial projects.

The Chief Secretary emphasized the need for an expedited procurement process for these new projects within the given timelines. He also urged upon the concerned to pursue the Lalla Ded Hospital project approval with the World Bank at the earliest so that the same would be taken up further.

The meeting also reviewed the progress on upgrading 49 dewatering stations, advancing Lalla Ded Hospital project documentation, completing the State Emergency Operation Center structure and ongoing electro-mechanical component procurement.

Besides, the implementation of an Integrated Operational Forecasting System (IOFS), Digital Risk Database (DRDB) and Supervisory Control and Data Acquisition (SCADA) systems was reviewed in detail.

Notably, it was informed that the Supervisory Control and Data Acquisition (SCADA) project has connected 72 out of 80 dewatering stations and is ready to be operated remotely by the Srinagar Municipal Corporation.

 

 

 

 

 

 