• About us
  • Contact us
  • Our team
  • Terms of Service
Sunday, August 17, 2025
Kashmir Images - Latest News Update
Epaper
  • TOP NEWS
  • CITY & TOWNS
  • LOCAL
  • BUSINESS
  • NATION
  • WORLD
  • SPORTS
  • OPINION
    • EDITORIAL
    • ON HERITAGE
    • CREATIVE BEATS
    • INTERALIA
    • WIDE ANGLE
    • OTHER VIEW
    • ART SPACE
  • Photo Gallery
  • CARTOON
  • EPAPER
No Result
View All Result
Kashmir Images - Latest News Update
No Result
View All Result
Home TOP NEWS

CAG slams J&K govt over delay in construction of Srinagar-Leh transmission line

Images News Netwok by Images News Netwok
August 10, 2022
in TOP NEWS
A A
0
J&K’s power purchase bill set to hit all time high
FacebookTwitterWhatsapp

Srinagar: The Comptroller and Auditor General (CAG) of India has slammed the authorities over delay in taking decision for construction of Srinagar-Leh transmission line, saying it not only led to huge cost escalation but also caused a generation loss of 1,602.64 MUs and an extra expenditure of Rs 700.25 crore due to billing of deemed generation to Power Development Department.

In its report, CAG revealed: “Due to delay in taking decision for construction of the line, not only huge cost escalation had occurred but there was also a generation loss of 1,602.64 MUs and an extra expenditure of Rs 700. 25 crore due to billing of deemed generation to Power Development Department.”

Related posts

Chasoti Tragedy: Death toll climbs to 60, 100 injured, scores still missing as rescue operations continue for third day

Chasoti Tragedy: Death toll climbs to 60, 100 injured, scores still missing as rescue operations continue for third day

August 17, 2025
Lieutenant Governor Greets People on Independence Day

LG ensures reconstruction of homes damaged in Kishtwar village

August 17, 2025

In 2003, the Government of India announced a special package for J&K comprising a 375 km transmission system project from Srinagar to Leh via Kargil with four substations at Drass, Kargil, Leh and Khaltsi at an estimated cost of Rs 377.52 crore.

However, in September 2004, the scope of the transmission system was revised by shifting overhead line between Gagangir to Zojila Pass to underground line along with change in the transmission capacity at Kargil sub-station, being an avalanche prone area, which led to an increase in estimated cost to Rs 633.79 crore,” reads the report.

On December 15, 2004, the Government of Jammu and Kashmir accorded its approval for execution of the project by Power Grid Corporation of India Limited (PGCIL); however, the project was put on hold by the Ministry of Power on June 27, 2005.

The project was finally approved by the Government of India in January 2014 at an estimated cost of Rs 1,788.41 crore with scheduled completion period of 42 months from the date of release of first installment of fund. The first installment was received on March 01, 2014 and the approved commissioning schedule of the project was September 2017.

The project was planned and implemented by PDD and commissioned in January 2019 with a delay of 16 months from the scheduled date.

The CAG has said that due to time lag in approval/implementation of the transmission system, completion cost has escalated to Rs 1,583.36 crore from initial estimated cost of Rs 633.79 crore.

The audit further noticed that in the absence of national grid connectivity due to delay in commissioning of Srinagar-Leh transmission system, Chutak and Nimmo Bazgo hydro power stations were operated in isolation mode and could not be optimally utilized upto their designed capacity and their generation had to be curtailed up to the limited requirements of the Ladakh region only.

“As a result, 1,602.64 MUs of power could not be generated which resulted in generation loss,” the report states.

According to the report, NHPC raised a bill of Rs 1,166.56 crore for deemed generation from these two projects on the Power Development Department.

“Actual generation from these two power stations was only 736.75 MUs (29 percent) against their generation capacity of 2,524.36 MUs. The Central Electricity Regulatory Commission, however, allowed NHPC to claim the tariff in respect of deemed generation. Accordingly, NHPC raised a bill of Rs 1,166.56 crore for deemed generation on Power Development Department (J&K) and received part payment of Rs 267.59 crore from the Power Development Department and the balance amount is yet to be paid,” the report states. (With KNO Inputs)

Previous Post

HC raps authorities for failing to preserve Sonamarg

Next Post

J&K govt failed to submit utilisation certificates for grants worth over Rs 10,000 Cr: CAG

Images News Netwok

Images News Netwok

Next Post
2018 nears its end, but CAG report yet to be made public in J&K

J&K govt failed to submit utilisation certificates for grants worth over Rs 10,000 Cr: CAG

Leave a Reply Cancel reply

Your email address will not be published. Required fields are marked *

ePaper

  • About us
  • Contact us
  • Our team
  • Terms of Service
E-Mailus: kashmirimages123@gmail.com

© 2024 Kashmir Images - Designed by GITS.

No Result
View All Result
  • TOP NEWS
  • CITY & TOWNS
  • LOCAL
  • BUSINESS
  • NATION
  • WORLD
  • SPORTS
  • OPINION
    • EDITORIAL
    • ON HERITAGE
    • CREATIVE BEATS
    • INTERALIA
    • WIDE ANGLE
    • OTHER VIEW
    • ART SPACE
  • Photo Gallery
  • CARTOON
  • EPAPER

© 2024 Kashmir Images - Designed by GITS.