• TOP NEWS
  • CITY & TOWNS
  • LOCAL
  • BUSINESS
  • NATION
  • WORLD
  • SPORTS
  • OPINION
    • EDITORIAL
    • ON HERITAGE
    • CREATIVE BEATS
    • INTERALIA
    • WIDE ANGLE
    • OTHER VIEW
    • ART SPACE
  • Photo Gallery
  • CARTOON
  • EPAPER
Tuesday, July 1, 2025
Kashmir Images - Latest News Update
Epaper
  • TOP NEWS
  • CITY & TOWNS
  • LOCAL
  • BUSINESS
  • NATION
  • WORLD
  • SPORTS
  • OPINION
    • EDITORIAL
    • ON HERITAGE
    • CREATIVE BEATS
    • INTERALIA
    • WIDE ANGLE
    • OTHER VIEW
    • ART SPACE
  • Photo Gallery
  • CARTOON
  • EPAPER
No Result
View All Result
Kashmir Images - Latest News Update
No Result
View All Result
Home CITY & TOWNS

Div Com reviews progress on Z- MORH/ Zojila tunnels

Images News Netwok by Images News Netwok
August 11, 2020
in CITY & TOWNS
0
‘SFC to axe all female Russian poplars within a week’

SRINAGAR: Divisional Commissioner Kashmir, Pandurang K Pole today chaired a meeting to review pace and progress made on Z- Morh and Zojila tunnels connecting Kashmir with the Ladakh region.

At the outset, Executive Director, NHIDCL, gave a detailed PowerPoint Presentation (PPP) of Z-Morh tunnel, construction of approach roads, lanes, protective walls, drains besides the road and other projects.

Related posts

Rana reviews PMGSY projects in Poonch

July 1, 2025

Committee on Public Undertakings holds meeting in Srinagar

July 1, 2025

The chair was informed that the work process was going on in full swing and against 169 meters target 216 meters were achieved instead in the month of July.

Div Com directed concerned to arrange cent percent manpower arrangement and install all machinery and equipment within 15 days period to expedite the work process.

He instructed concerned to mobilize the manpower before August- 20 and establish level-2 quarantine facility to facilitate them better medical treatment in case any employee contracts COVID-19 infection.

The meeting was informed that the deadline for the tunnel is December-21, 2023 however,  a bonus up to Rs 400 crores shall be provided to the concerned agency if the project is completed before it’s set deadline.

It was further informed that 14.083 km long Zojila tunnel is constructed to facilitate all weather connectivity between Srinagar and Leh.

The meeting also deliberated over various other projects to be taken up by NHIDCL.

The Div Com emphasized on early clearance of pending liabilities of vendors, workers, hoteliers, shopkeepers and instructed that the concerned committee shall look into the issue and address it on priority.

He also directed concerned to identify alternate sites for the dumping purpose instead of the earlier one which is close to the stream besides instructed on early identification of sites for the helipad.

Among others, the meeting was attended by Executive Director, NHIDCL, Anand Pahal, General Manager Project, Praveen Ahlawal and others concerned.

Previous Post

Religious heads have huge role towards creating awareness regarding COVID-19: Advisor Baseer Khan

Next Post

Jammu industrialists seek LG’s intervention in saving MSME sector in J&K

Next Post
Dalit woman alleges discrimination, threatens to embrace Islam

Jammu industrialists seek LG’s intervention in saving MSME sector in J&K

Leave a Reply Cancel reply

Your email address will not be published. Required fields are marked *

ePaper

  • About us
  • Contact us
  • Our team
  • Terms of Service
E-Mailus: [email protected]

© 2024 Kashmir Images - Designed by GITS.

No Result
View All Result
  • TOP NEWS
  • CITY & TOWNS
  • LOCAL
  • BUSINESS
  • NATION
  • WORLD
  • SPORTS
  • OPINION
    • EDITORIAL
    • ON HERITAGE
    • CREATIVE BEATS
    • INTERALIA
    • WIDE ANGLE
    • OTHER VIEW
    • ART SPACE
  • Photo Gallery
  • CARTOON
  • EPAPER

© 2024 Kashmir Images - Designed by GITS.