• About us
  • Contact us
  • Our team
  • Terms of Service
Tuesday, August 26, 2025
Kashmir Images - Latest News Update
Epaper
  • TOP NEWS
  • CITY & TOWNS
  • LOCAL
  • BUSINESS
  • NATION
  • WORLD
  • SPORTS
  • OPINION
    • EDITORIAL
    • ON HERITAGE
    • CREATIVE BEATS
    • INTERALIA
    • WIDE ANGLE
    • OTHER VIEW
    • ART SPACE
  • Photo Gallery
  • CARTOON
  • EPAPER
No Result
View All Result
Kashmir Images - Latest News Update
No Result
View All Result
Home BUSINESS

Bharatmala Pariyojana to get delayed by 4 years: ICRA

Press Trust of india by Press Trust of india
June 11, 2020
in BUSINESS
A A
0
Bharatmala Pariyojana to get delayed by 4 years: ICRA
FacebookTwitterWhatsapp

New Delhi:  The first phase of the ambitious Bharatmala Pariyojana (BMP) that was scheduled for completion in 2021-22 is now likely to get completed by 2025-26, rating agency ICRA said on Wednesday.

Till February 2020, a total of 246 road projects with an aggregate length of about 10,100 km were awarded under BMP Phase-I at a total cost of Rs 2.38 lakh crore.

Related posts

Rise in repatriation sign of mature market: RBI Guv on moderation in net FDI

RBI has not lost sight of growth amid tariffs, geopolitical uncertainties: Malhotra

August 26, 2025

Farmers submit memorandum to Union agriculture minister; seek MSP law

August 26, 2025

“The Bharatmala Pariyojana (BMP) Phase–I is likely to be delayed by four years and get completed by FY2026 instead of earlier envisaged FY2022,” ICRA said.

Saying that till February projects worth Rs 2.38 lakh crore were awarded under BMP Phase-I, ICRA said the average cost of award stood at Rs 23.80 crore per km, which is 54 per cent higher than initial estimated cost of Rs 15.52 crore per km.

The land acquisition cost for NHAI, it said, increased at a CAGR of 27 per cent from FY2007 to FY2019 from Rs 0.21 crore per hectare to around Rs 4 crore per hectare.

This along with prudent bidding by developers at a premium when compared to NHAI’s base price has resulted in significantly higher awarded cost for BMP Phase-I when compared to initial estimates.

Further as per ICRA’s estimates, the prevailing uncertainty due to COVID-19 and the consequent impact on valuations could delay asset monetisation plan of NHAI through toll-operate-transfer (TOT) auctions and launch of infrastructure investment trust (InvIT).

Depending on how quickly the normalcy is restored, these plans could take off by end of FY2021. Therefore, 2020 is likely to be another year of muted awards.

Shubham Jain, Senior Vice President, Corporate Ratings, ICRA said, “As on March 2020, 16,219 km of BMP (around 47 per cent of BMP) was pending to be awarded. We expect the awards to remain in the range of 3,000-3,200 km in FY2021 and increase thereafter once NHAI completes its proposed fund raising through infrastructure investment trust.

“With pick up in awards starting FY2022, the Bharatmala awarding activity is expected to get completed by FY2023 only,” he added.

The Cabinet Committee on Economic Affairs (CCEA) approved the BMP Phase-I along with other programmes on October 24, 2017.

A total of around 34,800 km roads are being considered in BMP Phase-I, which also includes 10,000 km of balance road works under NHDP.

Estimated outlay for BMP Phase-I was Rs 5.35 lakh crore spread over five years between 2017-2022, as per the initial plan.

As per the revised funding plan dated September 2019, the dependence on market borrowings for BMP increased substantially by 72 per cent to Rs 3.59 lakh crore, while the budgetary allocations and contribution from central road and infrastructure fund were reduced by 46 per cent to Rs 1.83 lakh crore.

Consequently, borrowings of NHAI are expected to increase significantly and peak by FY2023 or FY2024; at the same time, NHAI’s asset monetisation also remains critical to meet the funding requirements of BMP Phase-I, ICRA said.

“About 21 per cent of BMP execution is completed as on March 31, 2020. Given the limited labour availability and productivity loss due to COVID-19, ICRA expects the pace of execution for FY2021 to remain low at 3,104 km and thereafter witness an increase by 10-15 per cent in FY2022 before peaking in FY2024. The pending works are expected to be completed by FY2026,” Jain said.

 

 

Previous Post

CHILD LABOUR – A GRUESOME ISSUE

Next Post

cartoon

Press Trust of india

Press Trust of india

Next Post
cartoon

cartoon

Leave a Reply Cancel reply

Your email address will not be published. Required fields are marked *

ePaper

  • About us
  • Contact us
  • Our team
  • Terms of Service
E-Mailus: kashmirimages123@gmail.com

© 2024 Kashmir Images - Designed by GITS.

No Result
View All Result
  • TOP NEWS
  • CITY & TOWNS
  • LOCAL
  • BUSINESS
  • NATION
  • WORLD
  • SPORTS
  • OPINION
    • EDITORIAL
    • ON HERITAGE
    • CREATIVE BEATS
    • INTERALIA
    • WIDE ANGLE
    • OTHER VIEW
    • ART SPACE
  • Photo Gallery
  • CARTOON
  • EPAPER

© 2024 Kashmir Images - Designed by GITS.