Dr Raghav Langer reviews progress on World Bank funded Jhelum Tawi Flood Recovery Project

Decrease Font Size Increase Font Size Text Size Print This Page

SRINAGAR: Secretary Planning Development and Monitoring, Dr. Raghav Langer, today reviewed the progress on the World Bank funded Jhelum Tawi Flood Recovery Project being executed by JKERA (Jammu and Economic Reconstruction Agency) at Civil Secretariat, Srinagar here today.

Chief Executive Officer, JKERA/JTFRP, Dr Syed Abid Rasheed Shah, while giving out the details of the World Bank funded JTFRP said that out of the total of 213 sub-projects taken up under (6) different components of the project namely Strengthening of Critical Infrastructure, Construction of roads and bridges, Strengthening of the Livelihoods, Strengthening of the Urban Flood Management, Strengthening of the Disaster Management Capacity and Contingency Emergency Response work on 132 sub-projects has been completed till date and work on remaining 84 is in advanced stage of execution.

It was further informed that contracts worth Rs 1750.20 crores have been awarded and disbursements to the tune of Rs 1051.32 has been made under the project till date.

Executive Director, JKPCC which is executing work on (08) bridge and (03) road projects under JTFRP informed that work on all the bridges is in full swing while as work on (02) road upgradation projects has already been completed and work on Ambarpora-Haritar project is underway and expected to be completed very soon.

He said that JKPCC work on the Construction of an additional block at Lal Ded Maternity Hospital, Srinagar is also underway. Drawings for the proof checking of designs for the sub-structure have been received from IIT and work on the component is expected to be tendered at the end of this month.

Dr. Raghav Langar, Secretary, Planning Development and Monitoring Dept. directed the JKPCC to take up work on the remaining components of the prestigious project in a planned and coordinated manner and simultaneously go for parallel activities like procurement of medical equipment for the project.

Dr. Raghav also asked the JKPCC officers present in the meeting to ensure the completion of all works allotted to it under JTFRP within the set timelines.