Power supply to remain affected in Budgam

Decrease Font Size Increase Font Size Text Size Print This Page

BUDGAM, JULY 22: According to Superintending Engineer, EM&RE Circle IIND Srinagar, due to some technical snag in 6.3 MVA Power transformer at Receiving Station Budgam, the entire load of the receiving station is to be catered through a single 10 MVA power transformer, as such Power Supply to the metered feeders namely Budgam town and JNV shall be restricted to 18 to 19 Hrs a day.

In non-metered feeders namely Jawalapora, Nasrullahpora, Bemina, Old Budgam and Shoolipora shall be restricted to 11 to 12 Hrs a day.

This disruption shall remain till another 10 MVA power Transformer is installed within a week’s time. The inconvenience to the general public is deeply regretted.